 |
Fig: Zeiss Contura G2 CMM |
| Foundation Isolation Solution provided by Dynemech |
Isolated foundation for Carl ZEISS CMM make contura G2
X/Y/Z measuring - 700/1000/600 mm
Machine Weight: 1550 Kg.
| Size of concrete block |
1900mm x 2200mm x 1000mm. |
Total weight of Machine
& Concrete Block |
12000Kgs. |
| Foundation Pit Size |
2100mm x 2400mm x 1100mm. |
Foundation Isolation
Solution |
Dynemech's Foundation Insulation Sheet - 75mm thick. |
|
 |
| Fig: Line Diagram for Dynemech Foundation Isolation for CMM Machines. |
Guide Lines:
- 1. Make a pit as per the recommended size – 2100 x 2400 x 1100 mm.
|
|
- 2. Pit should be 100% water proof; check ground water conditions.
|
|
- 3. The inner surface of the pit should be clean, dry & smooth.
|
|
 |
|
| Fig: Pit Construction |
|
- 4. As per the detailed layout supplied by Dynemech, place vibration damping plate set Dp Paste them to the pit base using – Pidlite SR-505 adhesive.
|
|
- 5. Place filler foam in the gaps between the Insulation plate set Dp. Paste them to the pit surface.
|
|
- 6. Place PVC on the entire pit surface and side walls. Seal the overlapping joints of the PVC sheet with adhesive tape so that the concrete water should not leak in to the pit base.
|
|
- 7. Place 25mm thick wooden board layer and joint should be sealed with adhesive tape. This will act as a support for the initial concrete pour.
|
|
- 8. Place another layer of PVC sheet on the pit base and the side walls joints sealed with adhesive tape.
|
|
  |
|
| Fig: Pit after placing Dynemech Insulation Sheet and Filler Foam. |
|
- 9. Pour concrete up to a depth of 150mmand allow it to dry, this will act as a compression plate. After drying the compression plate erect reinforcement and pour concrete in the rest of the concrete block volume. Concrete should be poured in layers of 300mm+300mm+350mm to complete a depth of 1100mm, allow each layer to dry and pour another layer.
|
|
- 10. The concrete block and the pit tub should not come in contact with each other.
|
|
- 11. Care should be taken that the concrete or concrete laced water should not leak in to the insulation plate area.
|
|
- 12. The side gaps may be filled with rubberised cork scrap.
|
|
 |
|
| Fig: Dynemech Isolated Foundation Solution |
Download Case Study - Foundation Isolation Zeiss CMM